Land and perc tests: before you buy or build
The soil under a lot decides whether it can take a septic system, which kind, and how much of your budget it will eat.
The short answer
Before buying land that will need a septic system, get a perc test or soil evaluation — ideally as a condition of the purchase. It tells you whether a system can be permitted and what type, which is the difference between a roughly $10,000 conventional system and a $25,000 mound or aerobic unit, or land that can't be built on at all.
In this section
Land-buying checklist for septic
- Ask the county for any existing perc or soil records on the parcel.
- Make the purchase contingent on a passing soil evaluation.
- Check setbacks from wells, streams, property lines and slopes against the lot's size and shape.
- Ask whether a reserve drain field area must be set aside.
- Price the system type the results allow before closing.
Setbacks that shrink the buildable area
A lot can pass a perc test and still not fit a system once the required distances are applied. These are typical minimums; your state and county set the real ones, and they are often larger for drain fields than for tanks.
| Distance from | Typical minimum |
|---|---|
| Private well to drain field | 50 – 100 ft |
| Private well to septic tank | 50 ft |
| House foundation to tank | 5 – 10 ft |
| House foundation to field | 10 – 20 ft |
| Property line to field | 5 – 10 ft |
| Stream, lake or wetland to field | 50 – 100 ft or more |
Typical ranges only. Check the county's septic rules before you buy.
How long the septic step takes
Budget one to three months from ordering a soil evaluation to having a septic permit: the test itself takes a day or two, but scheduling the tester, the design and the county's review each add weeks, and spring is the busiest season. Installation then takes a few days to two weeks depending on the system.